The construction process for the bridge main girders includes steel girder construction, deck plate construction, wet joint construction, steel girder construction can be cantilever assembly, bracket assembly or jacking construction, which can be reasonably selected according to the construction environment and schedule requirements. For bridges crossing rivers, the construction methods available are limited by the conditions, cantilever assembly and bracket assembly steel girder installation duration is long, the site is difficult to achieve, so the jacking construction is used, first with the tire frame assembly steel girders, continuous jacking site environmental impact is reduced. The force analysis of the structure during the whole process of jacking is carried out, which can be used as a reference for similar projects.